The Buteline Plumbing System is designed to be used with complete confidence. You will get a simple, controlled accurate joint every time. Below is a quick installation guide (you can also download the Solder Tail Installation Instructions as a PDF):

Before commencing any work involving heat processes, be sure to check that hot work is permitted.

Step 1  Cut Copper Pipe

Cut the copper pipe to length, ensuring the end is square.
Clean, and apply flux ready for soldering.

 

 

 

 

 

 

Step 2  Slide on Buteline Solder Fitting Socket

Slide the solder fitting socket onto the copper pipe, ensuring that the aluminium and plastic clamp ring assembly has been removed.

 

 

 

 

 

Step 3  Solder Joint

Using suitable lead-free solder, make a solder joint between the fitting and the copper pipe.

 

 

 

 

 

Step 4  Slide on Buteline Clamp Ring

AFTER the solder joint has COOLED, slide the aluminium clamp ring assembly onto the PB tail of the fitting, ensuring it goes fully up to the fitting shoulder.

 

 

 

 

 

 

Step 5  Insert Buteline Pipe

Simply insert the PB pipe into the Buteline fitting and push fully home to the shoulder of the fitting.

 

 

 

 

 

Step 6  Clamp

Clamp the Buteline fitting, using ONLY the Buteline clamp tool.

Position the Buteline clamp tool squarely, approximately 2mm in from  the end of the clamp ring.

Close handles to stops, hold in the tightly closed position for a moment  to ensure that the flow of material is performed. 

Open and remove the tool.

 

Step 7  All complete!

Installing the Buteline Plumbing System is quick and sure and always provides a visual indicator of joint completion.

As you can see, the process of using the Buteline system is quick, simple and highly efficient.